
The Penang Hill cable car is now targeted to open in the fourth quarter of 2027. In 2025, however, the state expected construction to end in December 2026. As a result, opening is now about a year later.
Penang Chief Minister Chow Kon Yeow gave the latest figures on 21 August. The project is 32 per cent complete, he said. Meanwhile, physical works should finish by August 2027. The first of 15 towers, Tower 3, is up.
This report sets out how the dates moved and what has been built so far. It also tests whether the pace can meet the new target. For now, the state has not announced a ticket price.
How the Penang Hill cable car date moved from 2026 to 2027

CJ.MY reported in May 2023 that construction was tentatively set for the second quarter of 2024. Later, at the June 2024 groundbreaking, Penang Hill Corporation said work would finish by 2026.
In June 2025, Chow said completion was due by December 2026. A three-month trial would follow before opening. In January, State Infrastructure, Transport and Digital Committee chairman Zairil Khir Johari put operations at June 2027.
By July, however, Chow said completion was expected in August 2027. Reports link the delay to months of heavy rain. On 21 August, he said operations should start in the fourth quarter. In short, the state’s own target has moved at every update.
In total, completion has moved eight months, from December 2026 to August 2027. Opening has moved from the second quarter to the fourth quarter of 2027, a shift of two quarters.
What the Penang Hill cable car has built so far

Progress stood at 28 per cent on 5 April and 31 per cent on 10 August. It reached 32 per cent on 21 August. As a result, all underground works are complete, and construction has moved above ground.
The line needs 15 towers. To limit forest impact, Penang Hill Corporation cut the number earlier. Five stand inside the forest reserve, and ten stand outside it. So far, only Tower 3 is up. It stands 15 metres high in the Botanic Gardens area, and taller towers follow.
Read more: Penang Hill Cable Car project to feature Doppelmayr system
Read more: Penang Hill Cable Car project set to commence
Read more: SAM challenges approval of Penang Hill cable car project
The Penang Hill cable car will run 2.73 km from the Botanic Gardens to the summit. In total, it has three stations: Garden, Turn and Hill. The ride should take under 10 minutes, on 50 eight-passenger cabins moving at 6 metres a second. Doppelmayr supplies the system.
Chow put the cost at RM367.2 million in April. About 60 containers of Austrian equipment arrived in August, with another batch due in September and October. By comparison, in 2023, Hartasuma Sdn Bhd was to invest at least RM245 million. The difference is RM122.2 million, or 50 per cent. Capacity is about 1,000 passengers an hour, the corporation says.
Can the Penang Hill cable car finish by August 2027?

CJ.MY checked the pace. For example, progress rose four percentage points in the 138 days from 5 April to 21 August. That is about 0.9 points a month.
To reach 100 per cent by August 2027, the project must therefore add 68 points in about 12 months. That is about 5.7 points a month, roughly six times the recent pace. Chow expects faster work above ground, because it is easier to control.
Testing will follow. Penang Hill Corporation general manager Datuk Cheok Lay Leng said in May that safety testing takes two to three months. Add that to August 2027, and opening lands in October or November. That fits the fourth-quarter target.
Meanwhile, visitors are waiting for relief at the funicular. It carried 1.9 million riders in 2025, according to Chow. That is about 5,200 a day. The Penang Hill cable car is meant to ease those crowds. Still, the environmental objections raised in 2024 have not stopped construction. SAM challenged the approval, and the corporation replied.









Add comment