Nga Kor Ming wins award for reviving 1,726 sick housing projects

Housing Minister Nga Kor Ming won an Edge award after KPKT revived 1,726 sick housing projects covering 199,643 homes. Here is what remains unfinished.

Photo: KPKT Malaysia FB

Housing and Local Government (KPKT) Minister Nga Kor Ming has won The Edge Malaysia’s first Outstanding Public Service Award. It recognises the revival of sick housing projects. The ministry says it has revived 1,726 projects covering 199,643 homes. Their combined gross development value is RM158.16 billion, as at August 2026.

The award was presented at The Edge Malaysia Property Excellence Awards 2026 in Kuala Lumpur. For homebuyers, the number that matters is nearly 200,000 homes that were stalled and have moved again. A sick project is one that has fallen well behind its schedule. An abandoned project has stopped altogether.

Nga said the award belongs to the whole ministry, especially its special task force. He added that KPKT will keep tightening governance, monitoring and transparency. The goal is zero sick and abandoned housing projects by 2030.

Learn. Publish. Earn.

Got a story like this in you?

Learn to write factual stories with AI, get published on cj.my, and earn RM80–RM100 per story.

See Training Dates

From RM350 · November 2026 · Penang / KL / JB

Sick housing projects: what the 1,726 figure covers

Photo: KPKT Malaysia FB

The task force was set up in 2023 to deal with private projects that stalled. By August 2026, 147 projects had moved from sick to healthy status. They cover 29,900 homes and RM40.92 billion in gross development value.

A much larger group is finished. KPKT says 1,542 sick housing projects have received their Certificate of Completion and Compliance. These cover 163,621 homes worth RM115.74 billion. For buyers, that certificate is the step that allows them to move in.

CJ.MY added up the two groups. They come to 1,689 projects and 193,521 homes. That leaves 37 projects and 6,122 homes that the ministry’s statement does not itemise. The ministry’s breakdown by state is not yet public either.

For Malaysian SMEs Feature your business on Citizens Journal Malaysia
From RM1,000
Get featured →

The pace has also picked up. In December 2025, KPKT reported 1,333 projects revived. The new total is 393 higher. That is about 49 projects a month if the two cut-off dates are eight months apart.

Sick housing projects that are still unfinished

Photo: KPKT Malaysia FB

The award does not mean the problem is solved. As at 30 June, KPKT counted 303 sick private housing projects in Peninsular Malaysia. They involve 43,288 homes and RM40.25 billion in gross development value.

A further 100 projects were confirmed abandoned. They cover 27,998 homes and 14,961 buyers. Those are the households still waiting. The ministry said in July that Selangor has the most abandoned projects, at 41. Kelantan has 13 and Terengganu 11.

The figures cover only the Peninsula, so Sabah and Sarawak are not in that count. That means the 303 and 100 are a floor, not a national total. The 1,726 revived projects include national figures. The two sets of numbers should not be compared directly.

Abandoned projects also show up in other forms. Nga recently explained how abandoned vehicles can be scrapped faster under new guidelines.

Sick housing projects and the 2030 target

KPKT’s plan is to stop new problems from forming. The ministry’s reforms include the Housing Integrated Management System, electronic sale and purchase agreements and audits of Housing Development Accounts. It has also proposed a Real Property Development Act. The ministry says these allow earlier intervention.

The target is no abandoned projects by 2030. The ministry has repeated it since February, and Nga restated it at the award ceremony. The wording differs slightly between statements. Some say zero abandoned projects, others zero sick and abandoned.

Buyers should watch two things. The first is the next task force figures, which show whether the 303 sick projects fall. The second is whether the proposed Act reaches Parliament. Both will show whether the 2030 target is on track.

If you bought in a project that has stalled, keep your sale and purchase agreement and payment receipts. Ask the developer for a written timeline. Contact KPKT’s housing complaint channels if the project has already been classed as sick or abandoned.

Avatar photo

Yalinie Mathan

Yalinie Mathan is a writer, traveller and storyteller who believes the best stories are found off the main road. She contributes to CJ.MY with a focus on heritage, community and the people and places that define Malaysian life beyond the city. Whether she is exploring a century-old town or documenting a community's quiet resilience, Yalinie brings warmth and curiosity to everything she writes.